Digester Roofs - Coombabah

Client: Bechtel Australia Pty Ltd / BMA

Project Value: Approximately $1.2 M

Contract Type: Manufacture, Sandblasting & Painting, Delivery

Timeline: 18 months

Description: Package Water & Waste Water Treatment Plants

Digester Roof after FabricationDigester Roof after Fabrication 84,000kg Roof being lifted into place84,000kg Roof being lifted into place Roof #1 almost in placeRoof #1 almost in place

Project Objectives

Maxcon Industries was contracted by Abigroup to design, manufacture and install two roofs for Anerobic Digesters. The roofs were designed to capture methane gas, which is a by-product of the Biomass process.

Scope of Works

Maxcon Industries was engaged to design, procure, manufacture, project manage, test and paint the two digester roofs and transport them to site.

Special Considerations

The components were fabricated in our workshops and transported to site for final assembly and painting. Fabrication, sandblasting and initial priming was completed in the workshop therefore reducing onsite fabrication and painting time.

Fabrication

The two 84,000 kg digester roofs were manufactured in Maxcon Industries specialised fabrication workshop facility in Ipswich, west of Brisbane. The facility benefits from an assembly line approach to fabrication which encourages throughput and high productivity. Cut raw material enters the facility at one end then the fabricated items proceed via rail or overhead crane from general fabrication to finishing.  After sandblasting, the complete fabricated equipment is painted in our specialist environmentally friendly painting facility prior to packaging and dispatch. Workshop 1 is perfectly suited to fabricate the specialist equipment guaranteeing high quality product.

Delivery

50 loads were required to deliver the pre-fabricated sandblasted and primed components to site for final assembly. Maxcon Industries successfully completed the two 84,000 kg Digester roofs, which measured 23 m diameter and 2.5 meters high each, and delivered them to site with no problems.

 

Case Studies Listing

Package Treatment Plant

Case Studies

Package Treatment Plant

Client: Bechtel Australia Pty Ltd / BMA Project Value: Approximately $1.2 M Contract Type: Manufacture, Sandblasting & Painting, Delivery Timeline: 18 months Description: Package Water & Waste Water Treatment Plants    Project Objectives When BMA received approval to develop its Cavill Ridge mine project it appointed Bechtel as the Engineering... Read more

Digester Roofs - Coombabah

Case Studies

Digester Roofs - Coombabah

Client: Bechtel Australia Pty Ltd / BMA Project Value: Approximately $1.2 M Contract Type: Manufacture, Sandblasting & Painting, Delivery Timeline: 18 months Description: Package Water & Waste Water Treatment Plants    Project Objectives Maxcon Industries was contracted by Abigroup to design, manufacture and install two roofs for Anerobic Digesters. The roofs were... Read more

Twin Clarifiers - Bundamba

Case Studies

Twin Clarifiers - Bundamba

Client: Theiss, Black & Veatch Joint Venture Project Value: Approximately $700k Contract Type: Supply, Manufacture, Sandblasting & Painting, Delivery Timeline: 3 Weeks Description: 2 x Twin Clarifier Tanks    Project Objectives One of the most challenging  projects undertaken by Maxcon Industries was the design, manufacture, and installation of the ‘Bundamba Twins’ (as... Read more

Westbury Pipeline

Case Studies

Westbury Pipeline

Client: Cryeng Group Pty Ltd / BOC Limited Project Value: Approximately $1.8 M Contract Type: Manufacture, Testing, Sandblasting & Coating, Delivery Timeline: 14 months Description: 2 x 300,000L Cryogenic Vessels    Project Objectives BOC identified a site in Westbury Tasmania as the ideal location for a gas pipeline and the place for... Read more

Vacuum Insulated Pipes

Case Studies

Vacuum Insulated Pipes

Client: Bechtel Oil, Gas Chemical (QCLNG + APLNG) Project Value:  Contract Type: Supply, Manufacture, Sandblasting & Painting, Delivery Timeline: 24 Months Description: 8.0 Km Vacuum Insulated Pipe 6" to 60" Diameter    Project Objectives Maxcon Industries was contracted by Cryeng Group Pty Ltd (who was awarded the project by Bechtel Oil... Read more

Painting and Sand Blasting

Case Studies

Painting and Sand Blasting

Location: Blast room 1 and Paint Bays 1-4, Ipswich Blasting Capacity: Class 3 Blast with 60um Profile Painting Capacity: 18 metres W, 90 metres L, 10 metres H Description: State-of-the-Art Coating and Sand Blasting Facility     Workshop Facilities The factory complex has a floor area of approximately three thousand square... Read more