Package Treatment Plant

Client: Bechtel Australia Pty Ltd / BMA

Project Value: Approximately $1.2 M

Contract Type: Manufacture, Sandblasting & Painting, Delivery

Timeline: 18 months

Description: Package Water & Waste Water Treatment Plants

Package Water Treatment PlantPackage Water Treatment Plant Package Waste Water Treatment PlantPackage Waste Water Treatment Plant Kubota MBR Package PlantKubota MBR Package Plant

Project Objectives

When BMA received approval to develop its Cavill Ridge mine project it appointed Bechtel as the Engineering Construction Project Manager for the project. BMA required the supply and manufacture of steel water and waste water treatment plants that were high capacity with small footprints to reduce the environmental impact. Maxcon Industries was awarded the contract to procure, fabricate, prepare, paint and package the components of the treatment plants for site installation.

Scope of Works

The project was successfully delivered on specification without delay and there were no budget overruns. The plants were fabricated inside a covered workshop which ensured adherence to strict quality and timeline expectations by reducing steel exposure to weather. Once completed, the entire plants were moved into the onsite Sandblasting facilities, where they were prepared with protective coatings which were also applied on site.

Special Considerations

The client had extremely high expectations of project Quality Assurance documentation, reporting and accountability, which thanks to strenuous QA standards within Maxcon Industries, we were more than capable of providing.

Fabrication

Due to Maxcon Industries' state of the art painting and sandblasting facilities, handling time and costs were extensively reduced, thus providing a substantial saving to the client.

Delivery

Two Package Plants were transported and delivered in a convoy of trucks and re-assembled on-site. Each component was assembled perfectly; a direct result of the pre-assembly test carried out by Maxcon Industries in the workshop prior to delivery. 

Case Studies Listing

Package Treatment Plant

Case Studies

Package Treatment Plant

Client: Bechtel Australia Pty Ltd / BMA Project Value: Approximately $1.2 M Contract Type: Manufacture, Sandblasting & Painting, Delivery Timeline: 18 months Description: Package Water & Waste Water Treatment Plants    Project Objectives When BMA received approval to develop its Cavill Ridge mine project it appointed Bechtel as the Engineering... Read more

Digester Roofs - Coombabah

Case Studies

Digester Roofs - Coombabah

Client: Bechtel Australia Pty Ltd / BMA Project Value: Approximately $1.2 M Contract Type: Manufacture, Sandblasting & Painting, Delivery Timeline: 18 months Description: Package Water & Waste Water Treatment Plants    Project Objectives Maxcon Industries was contracted by Abigroup to design, manufacture and install two roofs for Anerobic Digesters. The roofs were... Read more

Twin Clarifiers - Bundamba

Case Studies

Twin Clarifiers - Bundamba

Client: Theiss, Black & Veatch Joint Venture Project Value: Approximately $700k Contract Type: Supply, Manufacture, Sandblasting & Painting, Delivery Timeline: 3 Weeks Description: 2 x Twin Clarifier Tanks    Project Objectives One of the most challenging  projects undertaken by Maxcon Industries was the design, manufacture, and installation of the ‘Bundamba Twins’ (as... Read more

Westbury Pipeline

Case Studies

Westbury Pipeline

Client: Cryeng Group Pty Ltd / BOC Limited Project Value: Approximately $1.8 M Contract Type: Manufacture, Testing, Sandblasting & Coating, Delivery Timeline: 14 months Description: 2 x 300,000L Cryogenic Vessels    Project Objectives BOC identified a site in Westbury Tasmania as the ideal location for a gas pipeline and the place for... Read more

Vacuum Insulated Pipes

Case Studies

Vacuum Insulated Pipes

Client: Bechtel Oil, Gas Chemical (QCLNG + APLNG) Project Value:  Contract Type: Supply, Manufacture, Sandblasting & Painting, Delivery Timeline: 24 Months Description: 8.0 Km Vacuum Insulated Pipe 6" to 60" Diameter    Project Objectives Maxcon Industries was contracted by Cryeng Group Pty Ltd (who was awarded the project by Bechtel Oil... Read more

Painting and Sand Blasting

Case Studies

Painting and Sand Blasting

Location: Blast room 1 and Paint Bays 1-4, Ipswich Blasting Capacity: Class 3 Blast with 60um Profile Painting Capacity: 18 metres W, 90 metres L, 10 metres H Description: State-of-the-Art Coating and Sand Blasting Facility     Workshop Facilities The factory complex has a floor area of approximately three thousand square... Read more

onlinecasinogo.com.au